China, the world's largest copper producer and consumer, is continuing to bring new capacity online through new smelters, refineries and expansion projects. New supply additions are being supported by the surging demand from the traditional consumption sectors including power, manufacturing, and construction. Demand is also being driven by new and sustainable energy infrastructure development as the country aims to peak carbon dioxide emissions by 2030 and achieve carbon neutrality by 2060
China
Daye Nonferrous’ new 400ktpa
copper smelter and refinery located in Huangshi is under construction and is
expected to start operations in the December quarter, lifting Daye’s total
refining capacity to 1Mtpa. Total
investment is estimated at CNY5.71bn (US$883m).

In 2022, Jiangxi Copper’s
65%-owned 180ktpa Guoxin Copper is planned to complete construction and
commence production. Jiangxi Copper acquired a 65% stake in Guorun Copper in
January 2019 and changed its name to Guoxin Copper. Jiangxi Copper started
construction of the Guoxin in December 2020 with an estimated capital investment
of CNY1.885bn (US$273.23m).
Also in 2022, Zhongtiaoshan
Nonferrous’ new Houma smelter and refinery is expected to come online. The old
50ktpa Houma stopped production in 2018 for relocation and expansion.
Zhongtiaoshan's original plan was to build a new Houma with the refining
capacity expanded to 350ktpa. However, the plan has been scaled back to
180ktpa. Investment for the new plan is estimated at CNY2.294bn (US$332.46m).
In 2021 and 2022, refining
capacity additions from smelter expansions include 300ktpa at Hechi Nanfang
Nonferrous’ Guangxi Nanguo Copper, 200ktpa at Shuikoushan Nonferrous’
Shuikoushan Copper, and 100ktpa at Zijin Mining’s Zijin Copper.
Three-staged development is
planned for Guangxi Nanguo Copper. Stage one commenced production in 2019,
producing 300ktpa of copper cathode. Stage two is planned to start up by the
end of 2022, with capacity expanded to 600ktpa. Stage three is scheduled by the
end of 2023 taking total capacity to 1Mtpa. However, stage three is not
included in AME’s base case supply forecast as it is in the feasibility study
stage.
Shuikoushan began operation
in 1982 and upgraded to be capable of producing 100ktpa in 2016. Further
expansion to 300ktpa is planned in 2021.
Zijin Mining plans to boost
Zijin Copper’s capacity to 400ktpa by adding 360 new electrolytic cells and
improving other critical pieces of smelter infrastructure. The upgrades are
expected to be completed in 2021.
Looking at Tongling
Nonferrous, the company completed the construction of its Ausmelt Expansion
Phase II Project at its Jinguan plant in June last year. Refining capacity has
been lifted by 140ktpa to 640ktpa. Meanwhile, Tongling Jinjian’s Relocation and
Expansion Project Stage One was put into operation in October 2020, taking its
refining capacity from 130ktpa to 200ktpa and adding an additional smelting
capacity of 60ktpa. The ramp-ups from the above two expansions underpin the
2021 Tongling Nonferrous’s group refined copper production target of 1.51Mt, 6%
higher than its 2020 production of 1.42Mt. AME forecasts Tongling Jinguan and
Jinjia to complete their ramp-ups from the expansion projects by 2022.

Indonesia
In connection with PT
Freeport Indonesia’s (PT-FI) 2018 agreement with the Indonesian government
associated with the extension of its mining rights from 2031 to 2041, PT-FI
committed to construct a new domestic smelting capacity by December 2023, which
will have a total processing capacity of 2Mtpa of copper concentrate.
Covid-19-related disruptions
have deferred the schedule for the new smelter. PT-FI also discussed with the
Indonesian government alternatives to its commitment to build a new smelter.
PT-FI is now planning to expand its existing smelter and refinery in Gresik,
East Java, by lifting the concentrate treatment capacity by 300ktpa (a 30%
increase). This reduces PT-FI’s new smelter development commitment from 2Mtpa
of concentrate to 1.7Mtpa.
After talks between PT-FI
and China’s Tsingshan Steel over the construction of the new smelter on the
eastern Indonesian island of Halmahera collapsed, PT-FI will now go ahead with
plans to build the new smelter near its existing copper smelting and refining
operations in Gresik, with a processing capacity of 1.7Mtpa of copper
concentrate. PT-FI signed an engineering, procurement and construction (EPC)
contract with Japanese engineering company Chiyoda in July this year to build
the new Gresik smelter with an estimated contract cost of US$2.8bn.
In Indonesia, a combination
of policies ranging from investment incentives for metal refiners to outright
bans on the export of unprocessed ores will be implemented in order to direct
investment into higher value-added mineral activities and away from exporting
raw minerals. Indonesia planned to bring forward the full ban of nickel ore to
January 2022, however, events around the pandemic have seen this pushed back to
June 2023. Copper is also expected to eventually face restrictions on exports
of unprocessed ore to encourage more domestic smelting capacities.
Rest of World
In the DRC, the government
also attempted many times to introduce similar bans in order to strengthen the
country's domestic smelting and refining operations. However, insufficient smelting capacity forced the government to reverse the decisions. The most recent ban ended in April 2021 and has now been replaced with waivers that will be issued on a case-by-case basis, which require the affected companies to submit applications.
Chinese investors are making
a big play in the DRC’s mining sector, particularly dominant in the
copper-and-cobalt-rich Haut Katanga and Lualaba areas of former Katanga
province. The Lualaba Smelter is 60%-owned by China Nonferrous Metal Mining
Group with the remaining 40% owned by Yunnan Copper of Kunming, China. The
smelter, which began operations in early 2020, will treat up to 150,000 wet
metric tonnes of copper concentrates from the recently-launched Kamoa-Kakula
Mine and produce copper blister containing approximately 99% copper that will
be returned to the mine, and collected by CITIC and Zijin.
China Nonferrous
Metal Mining and Yunnan Copper aim to double the Lualaba’s smelting capacity
with the Kamoa-Kakula’s phase two scheduled to start operation in the second
half of 2022. According to Kamoa-Kakula PEA, the project will expand by phases
and finally reach the processing capacity of 19Mtpa of ore. The construction of
a new smelter is also included in the 19Mtpa scenario.
Chinese players continue
expanding their global footprints in the mining and smelting sectors. Zijin
Mining acquired 63% of Serbia’s state-owned RTB BOR copper mining and smelting
company in 2018. Zijin plans to invest approximately US$1.26bn within six years
for technological upgrade and expansion of RTB BOR’s four mines and one
smelter. Zijin aims to lift refining capacity to 150ktpa of copper cathode from
the smelter at the end of its two-phase development plan.
Grupo Mexico is looking at a
multi-billion investment in smelting and electricity development in the Baja
California peninsula in Mexico. The company’s investment plan plots out the
next six years and includes US$2.3bn for expanding smelting capacity in Sonora
and US$815m to develop electricity infrastructure on the peninsula.
